Reliance Cements to set up 3MTPA Cement Grinding Unit & 60m3/h Readymade Concrete Mixing (RMC)
Unit of M/s Reliance Cement Co. Pvt. Ltd, at vill, Kudumalakunte, Taluka Gowribidanur,
Dist.Chikballapur, Karnataka.
The total power requirement is 25MW. It will be sourced from state transmission grid. Total
water requirement for the proposed plant will be 300KLD. The rain water harvesting facility
from roof top and other structure will be developed. The major part of total water requirement
shall be utilized for the cooling purpose. There will not be waste water generation from the
cement manufacturing process. Blow down and domestic waste water ( 22.5KLD) will be sent to
Common Sewage Treatment Plant of KIADB, and 25 KLD will be used for plantation. Of the
total area of 34.39 Ha, area around 5.15 Ha has been earmarked for greenbelt development /
plantation within the premises.
The public hearing was held on 09.01.2014 for the proposed Development of Phase I & II
Industrial Area at Gowribidanur, Chikkaballapura District, Karnataka by KIADB for grant of
Environmental Clearance. Since the project is situated within the existing Industrial Area, the
commitments made during the public hearing for the industrial area by the KIADB shall be
adhered to by the PP.